How a performance-funded energy project actually works
Performance funding is easy to describe badly. Described badly it sounds like something for nothing, which is the fastest way to lose a finance director in the first meeting. Described accurately it is a straightforward commercial structure with three parties, one measured number and a defined end.
No upfront capital. Approved measures can be funded through a Finance Partner and repaid from verified savings, so a share of the saving stays with you from the first month. Subject to design, credit approval and verified savings.
Any finance solution is provided under a separate customer agreement with a Finance Partner and remains subject to credit approval.
Three parties, three roles
The structure only makes sense once the three roles are separated. Most confusion about performance funding comes from collapsing them into two.
| Party | What they contribute | What they do not do |
|---|---|---|
| You, the operator | The site, twelve months of bills and operating data, and the credit standing that supports the finance. | You do not fund the equipment upfront on an approved project. |
| Enspara | Designs the measures, installs and commissions them, meters the result, and stays accountable for performance for the life of the agreement. | Enspara does not provide the finance. |
| The Finance Partner | Provides the finance to you under a separate agreement, and pays Enspara. | The Finance Partner has no role in deciding the measurement result. |
That last separation is worth pausing on. If the funder could adjudicate the measurement, every reported result would carry a conflict of interest. The measurement runs against an agreed baseline and is verified under the International Performance Measurement and Verification Protocol, on a plan you approved before installation. The method is set out in Without measurement, savings are an opinion.
What the site keeps, and when
From the first month a share of the verified saving stays with you as cash. The balance meets the finance payment over a multi-year term agreed for your project. When the term ends the payment stops and the whole saving stays with the site. The equipment and controls keep working.
The structure is designed to be cash-flow positive from the first month, subject to the approved structure. That phrasing is deliberate. It is a design intent that follows from the measures being selected and sized against your own baseline, and it is not a promise made before anyone has seen your bills.
This is not free equipment. It is a performance-based structure. The savings target, the finance term and the split between your retained saving and the finance payment are set for each site after Enspara has reviewed your data and designed the solution, and after the Finance Partner has approved credit. Nothing is committed until the baseline, the scope, the measurement method and the finance terms are agreed and signed.
The waterfall, step by step
Follow one dollar of energy cost through the structure and the commercial logic is visible in five steps.
- Baseline energy cost. The agreed, normalised cost of energy at the site before the project.
- Gross verified saving. Measured under the approved measurement and verification plan, against the adjusted baseline rather than against last year's invoice.
- Finance payment. Set per project. It depends on the approved design and on credit approval, and it is fixed by agreement rather than by the size of any single month's bill.
- Net retained saving. The cash that stays with the site each year during the term.
- Carbon reduction. Reported from the verified energy saving. Reported, not sold. Enspara does not promise carbon credits.
This illustrates the commercial logic. It is not a quoted offer. Savings, term and payment are set per site after design, credit approval and signed terms, and are verified against an agreed baseline.
How the target is tested
Verified performance is reported against the contracted savings target, tracked monthly and reconciled annually. The arithmetic is simple once the baseline is agreed.
Worked example, not a project. If the adjusted baseline is 100 MWh and actual use is 52 MWh, the verified saving is 48 MWh. Against a 50 MWh contracted target, achievement is 96%.
Where verified savings fall short after the agreed adjustments, Enspara investigates and corrects the causes it controls. That is an engineering obligation on the party that designed the system, which is where it belongs. Because the Finance Partner does not decide the measurement result, a shortfall is a technical conversation rather than a commercial standoff.
The questions finance directors ask first
Is the finance guaranteed?
No. Finance is provided under a separate agreement with a Finance Partner and remains subject to credit approval. Not every site or every measure will support a performance-funded structure. Data quality, operating stability and creditworthiness all matter, which is why the assessment comes before any commitment.
Who owns the equipment?
Title to the equipment is set out in your finance agreement with the Finance Partner and in the site Addendum with Enspara, and depends on the finance product used for your project. Enspara explains the ownership position for your project in writing before you sign anything.
What happens when the term ends?
The finance payment stops and the whole verified saving stays with the site. The equipment and controls keep working. Ongoing monitoring and support after the term are arranged separately if you want them.
What do I actually sign?
A mutual non-disclosure agreement before you share bills and operating data. If you proceed after the assessment: the Energy Saving Framework Agreement with Enspara, a site Addendum for each site, your approval of the M&V Proposal Plan, a separate finance agreement with the Finance Partner, and a purchase order to Enspara. Installation starts once the Finance Partner's payment conditions are met.
What happens at hand-over?
Installation closes with a Practical Completion Certificate and a Defects Schedule, then Performance Acceptance. Performance accountability stays with Enspara for the life of the agreement.
Why the structure suits multi-site operators
An energy upgrade competes for capital against everything else a hospitality group could do with the same money: a refurbishment, a new site, a point-of-sale replacement. In that queue it usually loses, not because the return is poor but because the payback lands outside the horizon the board is working to. Performance funding takes the project out of that queue entirely. The measure is judged on whether it produces a verified saving large enough to carry its own payment, which is a narrower and more answerable question than whether it beats every other use of capital.
It also changes what is being bought. An operator funding equipment upfront buys a machine and hopes for a result. An operator in a performance-funded structure buys a result and holds one accountable party to it, with the measurement method agreed in advance and the equipment as the means rather than the deliverable.
The first step is smaller than the structure
None of the above starts with a finance application. It starts with twelve months of bills, 24 if available, plus interval data where it exists, for two representative sites. That is the input to the Two-Site Energy Profit Assessment, which produces a baseline, ranked opportunities, a site-tested business case and a measurement plan. The funding page sets out the full structure, and the case studies show the measures the structure pays for.